Phase Safe Electrical installs and maintains EV chargers for businesses: workplace charging for staff, depot charging for fleets, and chargers in customer, visitor and commercial car parks. We check your supply and switchboard capacity, plan the layout, carry out the electrical work and the associated building and site works, then test, certify and look after the chargers. We work for commercial and industrial clients across New Zealand, from bases in Wellington and Auckland.
Who needs commercial EV charging?
Any business or building that wants electric vehicles charged on its own site. That includes workplaces charging staff and pool cars during the day, operators charging vans and utes at a depot, retailers and hospitality venues offering charging to customers, and landlords or body corporates adding chargers to shared commercial or apartment car parks. Each setting needs a different charger speed, access arrangement and maintenance routine.
- Workplace charging. Staff and pool cars parked for most of the day suit slower AC chargers, often with access control.
- Fleet and depot charging. Vans, utes and pool vehicles that return to base overnight can charge slowly, with load management spreading the demand across the night.
- Customer and visitor car parks. Visitors stay for an hour or two, so faster charging and clear signage matter more. Chargers open to the public also bring a recommended annual assessment.
- Shared and body corporate car parks. Commercial buildings and apartment car parks run by a body corporate need agreement on where chargers go, how energy is metered and who pays.
We work on commercial sites only, so we don't install chargers at private homes.
Does a workplace need a dedicated EV charger?
Yes. EECA, the government's energy efficiency agency, says businesses are legally required to install dedicated EV chargers in a workplace rather than rely on the cable that plugs into a standard 3-pin outlet. WorkSafe's EV charging safety guidelines say Mode 1 charging from an ordinary socket is not permitted outside domestic premises, Mode 2 portable leads may not be used for public charging, and permanently connected Mode 3 (AC) and Mode 4 (DC) chargers may be installed and used.
What a site assessment checks
A site assessment works out how many chargers your site can carry, where they should go and what the job will involve, before you buy any hardware. EECA advises checking power capacity first, because it can limit the number, size and speed of the chargers you install. We look at the incoming supply, the switchboards, the cable routes, the car park layout and how your vehicles actually use it.
- Supply and demand. The size of the connection and how much of it the building already uses at its busiest.
- Switchboard capacity. Spare ways, protection and space for new circuits or a dedicated charger sub-board.
- Cable route and distance. How far each charger is from the board, and whether the route crosses concrete, asphalt or landscaping.
- How vehicles are used. How long they park, how far they drive each day and whether they all arrive at once.
- Exposure and connectivity. Weather, vehicle movements and public access at each bay, and whether networked chargers can get a data connection.
Supply and switchboard capacity
Every charger adds a large, steady load that can run for hours, on top of the building's normal demand. If the supply and switchboard have spare capacity, new circuits or a charger sub-board may be all you need. If they don't, the options are load management, a switchboard upgrade, or a larger connection from the local network, which brings in the lines company and your electricity retailer.
A capacity change needs confirmation from the network before work starts, and the retailer handles any metering changes, with charges set by each. Our page on distribution boards and switchboards covers board upgrades and sub-boards in more detail.
How load management lets more chargers share a supply
Load management shares the available supply between chargers, and between the chargers and the rest of the building, so you can install more charging points without paying for a bigger connection. Chargers slow down or take turns when demand is high and speed up again when it falls. EECA notes that smart chargers give you control over charging load and may avoid the need for a supply upgrade.
WorkSafe's January 2026 addendum to the guidelines expects load-managed charging in apartment building car parks to recharge a typical day's driving without raising peak demand. Smart functions are also on the regulatory agenda: in August 2026 EECA consulted on proposed minimum smart functions for new EV chargers over 2.4 kW sold in New Zealand.
AC or DC charging: which suits your site?
AC chargers suit vehicles parked for hours, such as staff cars during the working day and fleets charging overnight. DC chargers suit quick turnaround, such as customer car parks where visitors stay a short time, or fleets that need to charge between shifts. EECA puts smart AC chargers at 3.6–7 kW, adding 20–40 km of range an hour, and says a 30 kW DC charger adds about 100 km in 40 minutes.
| AC charging (Mode 3) | DC charging (Mode 4) | |
|---|---|---|
| How it charges | The vehicle's onboard charger converts AC to DC | The charger supplies DC straight to the battery |
| Typical speed (EECA) | 3.6–7 kW smart chargers: 20–40 km of range per hour | 30 kW: about 100 km in 40 minutes |
| Best for | Staff, pool and fleet vehicles parked for hours | Short visits and fast fleet turnaround |
| Supply impact | Modest per charger; adds up across many bays | Large; often needs a supply upgrade |
| Standard cited in the regulations | IEC 61851-1 | IEC 61851-1 with IEC 61851-23 |
Installation, testing and certification
A commercial installation covers the circuits and protection at the switchboard, the cable route to each charger, mounting on walls or pedestals, data connections for networked units, and commissioning. Installing a charger circuit is prescribed electrical work, so licensed electrical workers do it, test it and certify it with a Certificate of Compliance. An Electrical Safety Certificate follows no later than 20 working days after connection.
WorkSafe's guidelines add charger-specific requirements on top of the wiring rules. The 2019 edition calls for RCD protection that keeps working, or disconnects the supply, when DC fault current exceeds 6 mA, earth continuity monitoring, a lockable isolator on each charger circuit, at least IPX4 weather protection outdoors, protection from vehicle impact in public car parks, and charger socket-outlets at least 800 mm above the ground. Since 13 November 2025 the Electricity (Safety) Regulations 2010 have cited AS/NZS 3000:2018, with a New Zealand change requiring every RCD to suit the loads it serves, including DC fault currents, and they name IEC 61851 as the standard for AC and DC charging stations.
Building and site works, handled as part of the job
Most car park charging projects involve more than wiring. Cables may need trenching across a car park or cores through concrete, pedestal chargers need a footing, and bays usually need protection from vehicles, line marking and signage. We handle the associated building and site works as part of the job, so you deal with one contractor from site assessment to handover instead of coordinating several trades.
EECA lists signage, wheel stops, markings, access, security and lighting among the supporting infrastructure to plan for. We confirm at the site assessment what your car park needs and include it in the quote.
Ongoing maintenance of EV chargers
Chargers in daily use need regular inspection and testing, because cables and connectors get driven over, dropped and left in the rain, and the protective devices have to keep working. After installation we look after your chargers: checking leads, connectors and enclosures, testing RCDs and safety functions, keeping records and repairing faults.
For chargers that provide public charging, the 2019 guidelines recommend a periodic assessment within a year of connection and at least every 12 months after that, carried out by a person authorised under the Electricity Act (generally a licensed electrical inspector), with a tag on the charger showing when the assessment expires. Ordinary test and tag under AS/NZS 3760 cannot show that charging equipment is safe. Chargers can sit in your planned maintenance programme alongside the rest of your electrical equipment.
EV charging guides
Most businesses want to know what a commercial charger installation is likely to cost before they commit. Our cost guide sets out indicative published New Zealand figures for AC and DC chargers, dated and sourced, and the site factors that move a quote, from supply capacity to trenching.
- EV charger installation costIndicative NZ costs for commercial EV chargers and what moves the price: supply, distance, trenching, chargers.
Frequently asked questions
How high should an EV charger be installed?
The 2019 edition of WorkSafe's EV charging safety guidelines says the socket-outlet of a Mode 3 or Mode 4 charging station should be at least 800 mm above the finished ground or floor level, and as close as practicable to where the vehicle parks. In practice the height also depends on the charger model, the bay layout and how the cable reaches the vehicle's charge port.
Do workplace chargers count as public charging?
Not usually. The guidelines define public charging as charging at equipment intended for use by the public, such as roadside chargers and chargers in commercial facilities open to the public. Chargers in a staff-only car park that the public cannot reach are excluded. Customer and visitor chargers generally are public charging, which brings the recommended annual periodic assessment and tag.
How many EV chargers can our building support?
It depends on the spare capacity in your supply and switchboard, the charger power, and how many vehicles need to charge at the same time. Load management often lets a site run several chargers on a supply that could not carry them all at full power. A site assessment gives you the number.
Can staff charge from a normal power point at work?
No. EECA says businesses must install dedicated EV chargers in a workplace, and WorkSafe's guidelines do not permit Mode 1 charging from an ordinary socket outside domestic premises, or Mode 2 portable leads for public charging. A fixed charger on its own protected circuit is the safe and compliant option for staff, fleet and visitor charging.
Sources
- Electric vehicle charging safety guidelines and addenda (WorkSafe Energy Safety)
- Electric vehicle charging safety guidelines, 2nd edition, May 2019 (WorkSafe Energy Safety, PDF)
- Addendum to the Electric vehicle charging safety guidelines, 3rd edition, January 2026 (WorkSafe Energy Safety, PDF)
- Workplace EV charging (EECA)
- Consultation open on smart EV chargers, 13 August 2026 (EECA)
- Electricity (Safety) Regulations 2010, regulations 65 and 74C, and Schedule 4 clause 17 (New Zealand Legislation)
- Important update: changes to electricity safety regulations for electrical installations (WorkSafe, December 2025)
- Capacity change: what your network and electrician need to provide (Meridian Energy)