A building warrant of fitness (BWOF) is the owner's annual statement to the council that the specified systems in a building, such as sprinklers, fire alarms, lifts and emergency lighting, have been inspected, maintained and reported on for the past 12 months as the compliance schedule requires. It is required by section 108 of the Building Act 2004. For the electrical side of that work, see our BWOF and IQP inspections service.

What does a building warrant of fitness certify?

A BWOF certifies that the inspection, maintenance and reporting procedures in the building's compliance schedule were fully complied with during the previous 12 months. Its purpose, in the words of section 108, is to ensure the specified systems are performing, and will continue to perform, to their performance standards. It is not a general safety inspection of the whole building.

The BWOF is supplied in the prescribed form, Form 12 of the Building (Forms) Regulations 2004. It records the building's address, its current lawfully established use and occupant numbers, the year it was first built, the owner, where the compliance schedule is kept, and a signed statement that the procedures were fully complied with. Two kinds of attachment go with it:

  • Form 12A certificates. One from each independently qualified person (IQP) who carried out or supervised procedures, which together cover every specified system on the schedule.
  • Recommendations. Any recommendation from an IQP that the compliance schedule be amended so the systems keep performing to their standards.

The council does not issue the BWOF. Auckland Council's guidance says the owner or an agent completes Form 12 and supplies it.

Which buildings need a BWOF?

Any building with a compliance schedule needs a BWOF. Section 100 of the Building Act 2004 says a building that is not used wholly as a single household unit needs a compliance schedule if it has a specified system, or a cable car attached to it or serving it. That covers most commercial and industrial buildings: offices, shops, warehouses, factories, hotels, schools and public venues.

A building used wholly as a single household unit needs a compliance schedule only for a cable car. Specified systems are listed in Schedule 1 of the Building (Specified Systems, Change the Use, and Earthquake-prone Buildings) Regulations 2005, and the list is broad: an automatic door, an emergency light or a mechanical ventilation system can each be enough on its own. Our guide to compliance schedules and specified systems lists them all.

How the yearly BWOF cycle works

The BWOF cycle runs from one anniversary of the compliance schedule to the next. Through the year, IQPs and other people named in the schedule carry out the inspection and maintenance procedures and record them. At the anniversary, each IQP certifies their systems, the owner signs the BWOF, supplies it to the council with the certificates and pays the council's fee, and a copy goes on display in the building.

  1. First 12 months. When a compliance schedule is first issued, the council gives the owner a compliance schedule statement (Form 10). Section 105 requires it to be displayed publicly in the building for the first 12 months.
  2. Inspection and maintenance through the year. Each system is inspected, tested and maintained at the frequency the schedule states, and the results go into logbooks and reports.
  3. Annual reports and Form 12As. Each IQP or other person who carried out procedures signs an annual written report, and IQPs issue Form 12A certificates for their systems.
  4. Supply the BWOF. On the anniversary date the owner or agent supplies Form 12 with the attachments.
  5. Display it. A copy of the BWOF must be displayed where building users have ready access, such as the entry foyer or reception.
  6. Keep the records. Section 110 requires the annual reports to be kept with the compliance schedule for two years and produced to the council on request.

Who signs what in a BWOF?

Three parties sign or issue BWOF paperwork. The building owner, or an agent the owner authorises, signs the BWOF itself (Form 12). Each independently qualified person signs a Form 12A certificate for the specified systems they look after, and anyone who carried out procedures signs the annual written reports. The council receives and reviews the documents but does not sign the BWOF.

The owner carries the legal responsibility. Under section 105 the owner must make sure every specified system on the schedule is performing, and will keep performing, to its performance standards, and that a BWOF is supplied each year. Section 108A, in force since 26 November 2024, makes it an offence for an IQP to state that procedures were complied with when they were not. Our guide to what an IQP is covers how IQPs are registered.

What happens if a BWOF is late or procedures were missed?

A missing, late or false BWOF can lead to enforcement. Section 108 makes it an offence to fail to supply or display a BWOF, or to display a false or misleading one, with fines of up to $50,000 for an individual and $150,000 for a body corporate. A council that considers a BWOF incorrect, or the procedures not followed, must issue a notice to fix under section 164.

Wellington City Council says an incomplete or late submission can bring additional fees, infringement fines, a notice to fix or legal proceedings. If procedures were missed during the year, a valid BWOF cannot be supplied. Both Wellington City Council and Auckland Council follow MBIE guidance in that case: an IQP completes a Specified System Report and Declaration (S-RaD) for each affected system, and the council decides whether a BWOF Report and Declaration (B-RaD) can be displayed instead.

Will the council audit our BWOF?

Councils can inspect any building with a compliance schedule. Section 111 of the Building Act 2004 lets an authorised agent of the council inspect the building and its specified systems during normal working hours, to check that the BWOF and the annual reports are correct. Audits look at what is installed, what the records show and whether the BWOF is displayed.

Wellington City Council describes a three to five year on-site audit cycle as good practice, with the frequency reflecting the risk of the building's use. Auckland Council's published audit frequency is annual for high-risk uses involving sleeping, every three years for medium-risk assembly uses, and every five years for low-risk buildings such as offices, warehouses and restaurants.

How much does a BWOF cost?

A BWOF has two kinds of cost: the council's fee for processing it, and the fees charged by the IQPs and contractors who inspect and maintain the systems through the year. The council fee is set and published. The inspection and maintenance cost depends on how many systems the building has, how often each must be inspected, and the repairs found.

Council fees published at 16 November 2026:

Council BWOF fee
Wellington City Council $142 for 1 specified system or cable car, $283 for 2–10, $423 for 11 or more
Auckland Council $276 fixed annual renewal fee

Both councils also charge for on-site audits. Check your own council's current fees before budgeting, since every territorial authority sets its own.

Where electrical work fits in the BWOF

Several specified systems are electrical or depend on electrical supply and controls. Emergency lighting and emergency power are the clearest examples, and fire alarms, automatic doors, lifts, mechanical ventilation and smoke control all need power to work. Faults in those circuits show up in the inspections, and the repairs are electrical work for a licensed electrician.

Our guide to emergency lighting testing requirements explains how often it is tested and what the records need to show. If you also want the rest of the building's electrical installation checked, that is a separate commercial electrical inspection, because a BWOF covers only the specified systems on the schedule.

Frequently asked questions

Is a building WoF the same as a vehicle WoF?

No. A vehicle warrant of fitness is a periodic safety check of a car or other vehicle. A building warrant of fitness is the building owner's annual statement, under section 108 of the Building Act 2004, that the specified systems on the compliance schedule were inspected, maintained and reported on for the past 12 months. Both are called a WoF, but they come under different laws.

Who is responsible for the BWOF, the owner or the tenant?

The building owner. Sections 105 and 108 of the Building Act 2004 put the duties on the owner: keeping the specified systems performing, supplying the BWOF and displaying it. An owner can authorise an agent, such as a property manager, to supply the BWOF on their behalf, and a lease may pass some costs to tenants, but the legal duty stays with the owner.

Where does the BWOF have to be displayed?

Section 108(4) requires a copy of the BWOF to be displayed publicly in a place in the building that users have ready access to. Wellington City Council gives the entry foyer or reception area as examples. If the compliance schedule covers only a cable car, the copy is displayed in or near the cable car instead.

Do we need a BWOF if the building is empty?

Possibly. Auckland Council's guidance says a BWOF may still be needed when tenancies or the whole building are vacant, when specified systems have been decommissioned, or during renovation. Removing or changing a specified system means amending the compliance schedule, so check with your council before letting inspections lapse on an empty building.