Commercial & industrial electrical services, New ZealandOffice Mon–Fri 7.30am–5.00pm · 24/7 call-outs · info@phasesafe.co.nz

BWOF guide

What is an IQP (independent qualified person)?

What an IQP does, how councils register them, and the certificate they give the building owner.

Updated 16 November 2026

An IQP is an independently qualified person: someone a council has accepted as qualified to carry out or supervise the inspection, maintenance and reporting procedures for particular specified systems in a building, and to certify that those procedures were done. Their Form 12A certificates are what the owner attaches to the annual BWOF. For the electrical systems, see our BWOF and IQP inspections service.

What does IQP stand for?

IQP stands for independently qualified person, the term used in the Building Act 2004. Councils and the industry often say "independent qualified person", which means the same thing. Section 7 of the Act defines an IQP as a person accepted by a territorial authority as qualified to carry out or supervise some or all of the procedures for a specified system, and to certify them, whose acceptance has not been withdrawn.

So an IQP is accepted by a council for particular specified systems, not for a whole building, and the council can withdraw that acceptance.

What does an IQP do?

An IQP carries out or supervises the inspection, maintenance and reporting procedures that the compliance schedule sets for the specified systems they are registered for. That means the checks and tests at the frequencies the schedule states, the records of what was found and fixed, an annual written report, and at the end of each year a Form 12A certificate the owner attaches to the BWOF.

The work in a typical year looks like this:

  • Routine inspections and tests. At the intervals the compliance schedule sets for each system, using the procedure or standard the schedule names.
  • Records. Logbook entries and test results for each visit. Wellington City Council's guidance lists inspections and tests, preventative maintenance, faults found and repair work.
  • Annual written report. Section 110 requires the owner to obtain a signed annual report from each IQP or other person who carried out procedures, and to keep it with the compliance schedule for two years.
  • Form 12A. The certificate of compliance with inspection, maintenance and reporting procedures, stating that the procedures were fully complied with during the previous 12 months for the systems listed on it.
  • Recommendations. Where an IQP believes the compliance schedule needs amending so a system keeps performing, section 108(3)(d) requires that recommendation to be attached to the BWOF.

What is a Form 12A?

Form 12A is the IQP's certificate of compliance with inspection, maintenance and reporting procedures, prescribed by the Building (Forms) Regulations 2004 for section 108(3)(c) of the Building Act. It identifies the building and owner and states that the procedures in the compliance schedule were fully complied with during the previous 12 months for the specified systems named on it. Each IQP issues one for their systems.

The owner attaches all the Form 12As to the BWOF (Form 12). Section 108 requires that the certificates, taken together, cover every procedure in the compliance schedule. If one system has no Form 12A, the BWOF is incomplete. Our guide what is a building warrant of fitness explains how the forms fit together each year.

How are IQPs registered in New Zealand?

IQPs are registered by councils, not by a single national body. The Building Act 2004 requires only that a territorial authority accept the person, and councils run registers to record who is accepted for which systems. Several councils share regional registers. Applicants are assessed system by system, against criteria for qualifications, experience and knowledge of the Building Act.

For example:

  • Wellington City Council is the IQP registrar for the lower North Island and keeps the register for Wellington, Lower Hutt, Upper Hutt, Porirua, Kapiti Coast, Horowhenua, Masterton, Carterton and South Wairarapa councils. It accepts applications from individuals only, not companies, and registration runs for 12 months from 30 November.
  • Auckland Council runs its own register, with a public search by name, IQP number, council or type of system, and a published disciplinary policy for registered IQPs.

Because registration is individual, a company cannot itself be an IQP. Wellington City Council says organisations must register each employee or contractor who will work as an IQP, and that registering a manager who oversees unregistered staff is not suitable.

What qualifications does an IQP need?

The qualifications depend on the specified system. Councils publish minimum criteria for each one, usually combining knowledge of the relevant New Zealand or joint Australian and New Zealand standards and Building Code clauses, a trade qualification or registration where the work requires it, and several years of current industry experience. Experienced applicants without the formal qualifications may be assessed case by case.

Wellington City Council's criteria give a feel for the range. For emergency lighting (SS4), applicants need knowledge of AS 2293.1, AS/NZS 2293.1 and NZS 6742 and the Building Code clause F6 requirements, plus at least four years of relevant current industry experience. For emergency power from generator plant (SS14/1), they need knowledge of NZS 6104, must be a registered electrician, and need at least four years of relevant experience.

Every applicant must also show knowledge of the Building Act 2004, including sections 100 to 111, compliance schedules, BWOFs, the Building (Forms) Regulations 2004, notices to fix and council audits. Wellington City Council also asks for professional indemnity insurance details, two referee declarations for each system applied for, a code of conduct declaration and evidence of continuing professional development.

What are an IQP's legal duties?

An IQP must not certify procedures that were not done. Section 108A of the Building Act 2004, in force since 26 November 2024, makes it an offence for an IQP to state in a BWOF or any other document that the procedures for a specified system were complied with during the previous 12 months when they were not fully complied with. The maximum fine is $50,000 for an individual and $150,000 for a body corporate.

There is a defence where the failure came from a reasonable mistake or reasonable reliance on information supplied by someone else, or where the IQP took reasonable precautions and exercised due diligence. Councils also hold IQPs to account through their registers: Wellington City Council requires registered IQPs to follow its code of conduct and takes complaints through its IQP registration panel.

IQPs, electricians and electrical inspectors

An IQP, a licensed electrician and an electrical inspector are three different roles under two different laws. An IQP is accepted under the Building Act 2004 to inspect and certify specified systems. Electrical work on fixed wiring is prescribed electrical work under the Electricity Act 1992, and section 74 allows only authorised people, in practice licensed electrical workers, to do it or assist with it.

The roles meet in buildings where a specified system is electrical. An emergency lighting IQP may find a failed circuit that a licensed electrician then repairs, and the IQP records the repair before certifying. One person can hold both roles if they are licensed and also accepted by the council for that system. A full check of the wider electrical installation, beyond the specified systems, is a separate commercial electrical inspection.

What to ask before you engage an IQP

Before engaging an IQP, confirm which specified systems they are registered for and on which council's register, then check that on the council's search tool. Ask how they will follow your compliance schedule, and when you will receive the annual report and Form 12A ahead of the BWOF anniversary date.

  • Registration. Which systems, and which council register? Is the registration current?
  • Scope. Does the price cover every procedure in the schedule for those systems, including any yearly tests?
  • Repairs. Who fixes faults found during inspections, and how are repairs priced and recorded?
  • Timing. When will the Form 12A arrive relative to your anniversary date?

For emergency lighting in particular, our guide to emergency lighting testing requirements shows what a complete year of testing involves.

Frequently asked questions

What is an IQP inspection?

An IQP inspection is a check of a specified system, such as emergency lighting, a fire alarm or a lift, carried out or supervised by an independently qualified person following the procedure in the building's compliance schedule. The results are recorded, faults are reported for repair, and at the end of the year the IQP certifies the procedures on a Form 12A for the owner's BWOF.

How do I become IQP registered in New Zealand?

Apply to the council that keeps the IQP register for your region, for each specified system you want to work on. Wellington City Council, for example, accepts applications from individuals only and asks for evidence of qualifications, experience, Building Act knowledge, insurance, two referees per system and a signed code of conduct. Its registration runs for 12 months from 30 November and is renewed annually.

Can a building owner choose their own IQP?

Yes. The owner engages the IQPs, and Wellington City Council's guidance states that it is the owner's job to engage the IQPs the compliance schedule needs. Any IQP registered for the system with the council can be used. Many buildings have several IQPs, each certifying the systems they are registered for, and the owner collects all of their Form 12As for the BWOF.

How do I check whether an IQP is registered?

Use the council's IQP search tool. Wellington City Council's Find an IQP tool covers the councils on its lower North Island register, and Auckland Council's search lets you look up an IQP by name or number and filter by council or type of system. Check that the registration is current and covers the specific systems on your compliance schedule.

Sources